Stage 1

The first stage of this job consisted of our Freight division hauling a number of hoppers into the site where the job was to take place

Stage 2

The 20 ton picker was used to unload and place the hoppers on the customer’s bin pad

Stage 3

The bin crew retrofitted Westeel Rosco 19′ grain bins to 5,300 bushel capacity, and mounted them onto the hoppers

Stage 4

The crew also repaired some bins that had been blown over in a storm.

Stage 5

Bins were moved in from numerous locations

Job Complete...

Stage 6

Crew came back at a later date to drive anchors and tie down bins…

Stage 7

…and replace old lids with new center ring adapters and lids